ETE Line Side Civils Works

Location:
Wessex & Surrey

Date / Duration:
October 2017 - Ongoing

Client:

AM1 Projects

Work Scope:
Installation of New Cable Containment Routes ( Concrete )
Installation of New Cable containment routes ( GRP )
Installation of Steel support works for Cable containment routes
Installation of Buried duct routes
Construction of New concrete Bases
Supply of Safety Critical Staff


Sussex and Wessex H.V Power Renewals

Location
Sussex & Wessex

Date / Duration
September 2013 - November 2014

Client
Lowery Ltd

Work Scope:
Installation New H.V Cable with Network Rail Cable Train
Installation of UTX's
Installation of Buried Carson Duct H.V Route
Installation of all cable containment routes ( Concrete & GRP )
Concrete Base construction

ETE Enabling Works

Location
Sussex Inner and Outer

Date / Duration
June 2016 to date

Client
McNicholas Construction Services Ltd
Work Scope:
Installation of Tis Bases, Buried Duct routes through URX's and UTX's
Cable containment routes
Walkways and retaining walls
DC Cable Pulling
Tarmac Reinstatement
Traffic Management
Supply Site Supervisors
Supply Compound Manager

H.V Sussex Feeder Upgrades

Location
Wandsworth, West Croydon, Hassocks, Balcombe

Date / Duration
October 2014 - May 2016

Client
McNicholas Construction Services Ltd
Work Scope:
Installation of Cable Containment routes
Installation of H.V Feeder & Pilot Cables
Installation of Fibre cable
UTX and URX installation
Installation of Buried duct routes through full length platforms
Platform Re-instatements
Retaining walls to protect cable containment routes

Caterham ETE Upgrades

Location:
Whyleaffe South

Date / Duration:
December 26th 2016 - 5 Days

Client:
McNicholas Construction Services Ltd
Work Scope:
Construct Under Road Crossing Installing buried duct routes - 12 Metres x 2 m deep x 1.3m Wide
Provide Traffic Management for Road Closure
Excavate Platform to link up with Road Crossing 18metres x 1.8m Deep x 1.3m Deep
Excavate adjacent Platform for Buried DC Ducts 65metres x 1.8 deep x 1.3 wide
Installation of Ducting for DC Cables and back fill all excavated trenches
Permanent Tarmac Reinstatement to Road and both Platforms
Supply of Grab Wagons and Excavation Plant
Installation of cable containment routes ( Concrete Troughing )

East Kent Re-signalling Phase 2

Location:
Strood & Rochester

Date / Duration:
April 2016 - November 2016

Client:
Balfour Beatty Utilities ( BBUSL )
Work Scope:
Signalling Works
Remedial works to existing Cable Routes
Installation of New Cable containment Routes
Installation of New Buried duct routes
Recoveries of old redundant Signalling cables
H.V Cable diversion works
Installation of New Cable Containment routes ( Concrete, Plastic & GRP )
Installation of New H.V and pilot cables
Installation of Down Bank Retaining walls
Installation of New GRP Hand Rail
Recoveries of old redundant H.V Cables
Supply of Safety Critical Staff

Cross Rail W.O.E ( Western Outer Electrification )

Location:
Slough & Maidenhead

Date / Duration:
August 2016 - Ongoing

Client:
Balfour Beatty Utilities ( BBUSL )
Work Scope:
Installation of New Cable Containment Routes ( Concrete )
Installation of New Cable containment routes ( GRP )
Installation of Steel support works for Cable containment routes
Installation of Buried duct routes
Construction of New concrete Bases
Supply of Excavators and Dumpers
Hand Pulling ATF Cable for OLE
Supply of Safety Critical Staff